V
VHS
Hi,
I am currently using MS Project 2003 SP3.
Currently I am having 2 project plans and requires predecessors to setup
across project plans. As per the MS project help I followed the step and this
works fine. (Help > Linking Tasks > Linking tasks across projects).
As mentioned on the help -->
In the ID column, type the project name and ID number of the external
predecessor, separated by a backslash, for example Project1\1 for Task ID 1
in a file named Project1.
Question is -
a. Instead of Task ID can I use Unique ID? If so, how?
b. Reason for asking is, MS project automatically adds the tasks in both
project plans and this keep chaning the Task IDs. Though MS project
atuomatically updates the prdecessors/successors with that, the problem is if
we have multiple tasks to be setup for predecessors, this process becomes
very tedious. Instead if there is a way we can set the predecessors based on
we can note down the IDs on a notepad and than add all of them in one shot.
c. Is there any other better approach to handler such situation for external
dependencies?
Your earliest response will be of great help. Thanks in advance!
I am currently using MS Project 2003 SP3.
Currently I am having 2 project plans and requires predecessors to setup
across project plans. As per the MS project help I followed the step and this
works fine. (Help > Linking Tasks > Linking tasks across projects).
As mentioned on the help -->
In the ID column, type the project name and ID number of the external
predecessor, separated by a backslash, for example Project1\1 for Task ID 1
in a file named Project1.
Question is -
a. Instead of Task ID can I use Unique ID? If so, how?
b. Reason for asking is, MS project automatically adds the tasks in both
project plans and this keep chaning the Task IDs. Though MS project
atuomatically updates the prdecessors/successors with that, the problem is if
we have multiple tasks to be setup for predecessors, this process becomes
very tedious. Instead if there is a way we can set the predecessors based on
we can note down the IDs on a notepad and than add all of them in one shot.
c. Is there any other better approach to handler such situation for external
dependencies?
Your earliest response will be of great help. Thanks in advance!