Hello--
We have various schedules externally linked to other schedules in our
Terminal/Project Server environment. After a predecessor schedule changes,
the successor schedule would receive the changes (upon accepting the changes)
and the appropriate schedule dates would change in the successor schedule.
We are finding that the planned dates are changing properly in the successor
schedule via the external linking capability. However, we are finding that
the actual dates are NOT being updated in the successor schedule upon
accepting actual date changes from the predecessor schedule. This problem is
only occurring for one successor schedule that is very large in size (2500
line items). Do you think the size of the schedule is preventing the actual
dates from being updated?
Thank you.
We have various schedules externally linked to other schedules in our
Terminal/Project Server environment. After a predecessor schedule changes,
the successor schedule would receive the changes (upon accepting the changes)
and the appropriate schedule dates would change in the successor schedule.
We are finding that the planned dates are changing properly in the successor
schedule via the external linking capability. However, we are finding that
the actual dates are NOT being updated in the successor schedule upon
accepting actual date changes from the predecessor schedule. This problem is
only occurring for one successor schedule that is very large in size (2500
line items). Do you think the size of the schedule is preventing the actual
dates from being updated?
Thank you.