I have a director that want to have a published master schedule. So, he has
created a schedule that has tasks that are named identically to specific
summary tasks in the child schedules. He's established the dates for the
master project tasks to be identical to the summary project tasks and linked
the master project task to the summary task (Child schedule) in a FF
Relationship. He call this "Shadowing".
I consider this an improper way of using MSP. Will this approach have
impacts to the child schedule?
Thanks