J
Joe
We have 25 sub-projects in our department. Each project plan is managed by a
different project manager. The plans are linked through external links.
When one changes a linked task, the affected plan’s manager has to accept the
changes through the dialog box when he opens his plan.
Is there any way one person can view all outstanding external link changes
that have not been confirmed yet? For example, we could have 12 different
changes that have not been confirmed because some of the project managers may
not have accepted the changes. Is there any way someone with admin rights
can see which are open either through a master project plan or using PWA?
different project manager. The plans are linked through external links.
When one changes a linked task, the affected plan’s manager has to accept the
changes through the dialog box when he opens his plan.
Is there any way one person can view all outstanding external link changes
that have not been confirmed yet? For example, we could have 12 different
changes that have not been confirmed because some of the project managers may
not have accepted the changes. Is there any way someone with admin rights
can see which are open either through a master project plan or using PWA?