External Predecessors and Successors

R

Russ

I have many External Predecessors and Successors within my schedules.
When looking at Tools, Options, View - Cross project linking options for
'project name' some of the link show and some do not! It seems not to be
consistent which ones it omits and which ones it doesn't.

Has anyone seen (or not seen) this before?

Does anyone have a remedy?

Cheers,

Russ.
 
J

JulieS

Hello Russ,

I'm not sure I follow your post. When you look at a task view (Gantt
chart for example) do you see the bars for all the external
predecessors and successors? Does the external predecessor/success
task name appear in the task sheet?

The Tools>Options, View choice turns off or on the display.

What version of project and what service pack level are you working
with?

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 