External resources work

S

SusanB

I'm new to project and have MS Project Standard 2002. I have a Project file I
inherited from someone else. The tasks, start, finish, work, duration,
predecessors, and resource names fields are complete, mostly. Some of the
tasks are assigned to an "external" resource: our client, who gets 3 days to
review our stuff. I want Project to make space in the schedule for these 3
days, but to assign 0 hours to it, because I want the hours to be only my
company's billable hours. Is there a way to do this?
 