D
Darek
Hi,
I've got some strange of my projects' tasks.
I've made an external link between taskA in projectA and
taskB in projectB.taskA and taskB are connected with
finish-to-start link.
Now,
1) taskB is assigned with a resource and finished in 50%.
When I change the duration of taskA, the start date of
taskB does not change.
2) taskB is assigned with a resource and finished in 0%.
When I change the duration of taskA, the start date of
taskB changes properly.
Is this a normal behaviour or maybe I'm doing something
wrong ?
Is the only solution for this situation is using
milestones ?
I've got some strange of my projects' tasks.
I've made an external link between taskA in projectA and
taskB in projectB.taskA and taskB are connected with
finish-to-start link.
Now,
1) taskB is assigned with a resource and finished in 50%.
When I change the duration of taskA, the start date of
taskB does not change.
2) taskB is assigned with a resource and finished in 0%.
When I change the duration of taskA, the start date of
taskB changes properly.
Is this a normal behaviour or maybe I'm doing something
wrong ?
Is the only solution for this situation is using
milestones ?