Hi all,

How to Extract timephased data from database of MSP Server 2003, day by day.
Now I get directly from MSP local file, but the speed is very slow and
sometime COM cannot get exactly data because exception when call
objAssignment.TimeScaleData

Thanks
 
R

Rod Gill

Hi,

From the SQL Server Views look for the Tables named MSP_VIEW_ Some of them
have time phased data. Your projects have to be published to show latest
data.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 
M

Microsoft Communities

Hi,

I see the Tables named MSP_VIEW_ in SQL Server Tables. There are many table
and view, and I can’t understand field' responsibility...

Thanks for support.
 
R

Rod Gill

Open each one in turn and look at the data. I think timephase ones have by
day in the name but its been a long time since I use Project Server 2003.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top