One of my team member is trying to do the following thing:
Extract % Work completed over duration (non-cost earned value analysis) for
our client (4-5 projects / BU). The need is to extract/run this report at 80%
of project(s) duration (for performance analysis). The project(s) continues.
Now the problem is, if a project is at 85% of the duration and the PM wants
to extract the report of 80% (he forgot to do so at 80%), how can he do that
"or" if he can extract historical data, if yes, where?
Hope the question is understood,
Rgds,
Pranay
One of my team member is trying to do the following thing:
Extract % Work completed over duration (non-cost earned value analysis) for
our client (4-5 projects / BU). The need is to extract/run this report at 80%
of project(s) duration (for performance analysis). The project(s) continues.
Now the problem is, if a project is at 85% of the duration and the PM wants
to extract the report of 80% (he forgot to do so at 80%), how can he do that
"or" if he can extract historical data, if yes, where?
Hope the question is understood,
Rgds,
Pranay