Extracting Tasks on Critical Path Only

H

Hardip

Hi All

Is there a method to filter on only those tasks that are on the critical
path. I want to remove all non-critical tasks and publish this into
PowerPoint. I'm using Project 2000.

Thanks in advance to all who respond.

Regards,
Hardip
 
J

Jim Aksel

Insert a column called "Critical" which is a Yes/No field.
Filter on that column as needed.

You may also want to create a filter that hides work already completed.
We also routinely filter to "Critical Tasks and Remaining Work"

Let us know if you need more guidance.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 
M

Mike Glen

Hi Hardip,

Welcome to this Microsoft Project newsgroup :)

Try Project/Filtered for:.../Critical. If you don't want the summaries:
Tools/Options.../View tab deselect the showing of summaries, at the bottom
of the tab.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 