Failure submitting task updates using PSI

D

dmin72

Hi,
we've developed a C# event handler for Project Server 2007 based on
PSI using Visual Studio 2005 (.NET framework 2.0).

Similarly to CodePlex EPMTSST project we've successfully managed
timesheet data updating task actuals to PM with a single "Save and
Submit" on PWA timesheet page.
In short our event use impersonation with statusing web service
(statusing.asmx) to import timesheet (ImportTimesheet method) and then
submitting timesheet changes (SumitStatus method) back to PM for final
authorization.

We experienced a problem after submitting the first timesheet
assignment.
If we recall timesheet and change a single task actual with a value
more than 0 hours, PSI submit call work fine. Conversely if we change
task actual to 0 hours PSI seems to ignore that, leaving the previous
task assignment unchanged.
This only seems to happen when using PSI submit call to statusing web
service.

Does anyone know any issue about that?
Thanks.
 