R
rob.am.kuijpers
We use project professional for project managers and Project Web Access
for time sheet report and planning feedback by the teammembers. On the
homepage teammembers get a notification when they have not submitted
there time sheet. Sometimes the message "unsubmitt..." remaines on the
homepage although the employee has updated his timesheet with 30 hours.
When I use the function adjust actuals and change one day 8 hours in
8.1 hours the unsubmitted message disappears
One rootcause for this effect is when a team member add hours in the
timesheet. update. After that he adds hours and only uses the save
option
The SP1 is installed MS project professional 2003
(11.1.2004.1707.15)SP1
Internet Expl 6.0.2900.2180 SP2
Any idea ?
for time sheet report and planning feedback by the teammembers. On the
homepage teammembers get a notification when they have not submitted
there time sheet. Sometimes the message "unsubmitt..." remaines on the
homepage although the employee has updated his timesheet with 30 hours.
When I use the function adjust actuals and change one day 8 hours in
8.1 hours the unsubmitted message disappears
One rootcause for this effect is when a team member add hours in the
timesheet. update. After that he adds hours and only uses the save
option
The SP1 is installed MS project professional 2003
(11.1.2004.1707.15)SP1
Internet Expl 6.0.2900.2180 SP2
Any idea ?