B
Bob
Hi
I have this formula that provides an assessment of how earl or late a
task is wrt the baseline.
It displays in a Text field because of the combination of numbers and
text.
Any feedback is welcome.
IIf([Baseline Finish]>50000,"No
Baseline",FORMAT(((ProjDateDiff([Baseline Start],[Baseline
Finish])-ProjDateDiff([Start],[Finish]))/(IIf([Milestone] And
ProjDateDiff([Baseline Start],[Baseline
Finish])=0,1,ProjDateDiff([Baseline Start],[Baseline Finish])))),"0 %")
& IIf(Sgn(((ProjDateDiff([Baseline Start],[Baseline
Finish])-ProjDateDiff([Start],[Finish]))/(IIf([Milestone] And
ProjDateDiff([Baseline Start],[Baseline
Finish])=0,1,ProjDateDiff([Baseline Start],[Baseline Finish])))))=-1,"
Late"," Early"))
Cheers,
Bob
I have this formula that provides an assessment of how earl or late a
task is wrt the baseline.
It displays in a Text field because of the combination of numbers and
text.
Any feedback is welcome.
IIf([Baseline Finish]>50000,"No
Baseline",FORMAT(((ProjDateDiff([Baseline Start],[Baseline
Finish])-ProjDateDiff([Start],[Finish]))/(IIf([Milestone] And
ProjDateDiff([Baseline Start],[Baseline
Finish])=0,1,ProjDateDiff([Baseline Start],[Baseline Finish])))),"0 %")
& IIf(Sgn(((ProjDateDiff([Baseline Start],[Baseline
Finish])-ProjDateDiff([Start],[Finish]))/(IIf([Milestone] And
ProjDateDiff([Baseline Start],[Baseline
Finish])=0,1,ProjDateDiff([Baseline Start],[Baseline Finish])))))=-1,"
Late"," Early"))
Cheers,
Bob