Few question about processes on MS Project Server

A

Atul

Hi,

I was looking to see if there was a standard process for Resource management
on project server.

Also if i have a project plan created in Project Professional, can i update
it straight from the web and what is the process behind it.
 
D

Dale Howard [MVP]

Atul --

Your first question is way too broad for an answer here. Refer to the
following FAQ for information about documentation, books, and training on
Project Server:

http://www.projectserverexperts.com/Shared Documents/PS2003Documentation.htm

When you create a project in Microsoft Project Professional, you must
publish the project so that team members can see their task assignments on
their timesheet page in PWA. Team members update their task progress in PWA
and send their updates to the PM. The PM receives and approves/rejects task
updates from team members, and then process the approved updates into the
actual Microsoft Project plan. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top