M
Matt D.
Hi all,
Forgive me if this is obvious, but I haven't been using Project like this in
a while, so I forget what it can and can't do.
I work in a small company where we typically have 10-20 jobs running
simultaneously. We recently got all of our schedules into Project and have
them in a decent format for our workflow. We have each individual job in its
own MPP, and we have a master MPP that just imports all of the jobs for the
company. This is working for us, and in general we can get the status and
reports that we need by using the master MPP.
Anyway, here is a typical scenario we run into. Say a client is X days late
on something (like an approval), and they know it will cause at least a
day-for-day slip. We can update the MPP for that job accordingly, but I
would like to see what the impact is on the master schedule. Primarily, I
would like to identify milestones that occur on the same day (ie, did the
slip cause two milestones to occur on the same day) because this is bad for
our workflow. What is the best way to do this, other than scrolling a Gantt
chart up and down? Is this something that would need to be a VBA macro?
A related problem is that when I do reporting / grouping on our master
schedule, tasks don't make sense out of the context of the project name and
summary task name. Is there any way to do reporting / grouping that
concatenates project name, summary task names, with the job name onto a
single line? I have been playing with the various options without luck.
Thanks for any ideas or starting points.
Forgive me if this is obvious, but I haven't been using Project like this in
a while, so I forget what it can and can't do.
I work in a small company where we typically have 10-20 jobs running
simultaneously. We recently got all of our schedules into Project and have
them in a decent format for our workflow. We have each individual job in its
own MPP, and we have a master MPP that just imports all of the jobs for the
company. This is working for us, and in general we can get the status and
reports that we need by using the master MPP.
Anyway, here is a typical scenario we run into. Say a client is X days late
on something (like an approval), and they know it will cause at least a
day-for-day slip. We can update the MPP for that job accordingly, but I
would like to see what the impact is on the master schedule. Primarily, I
would like to identify milestones that occur on the same day (ie, did the
slip cause two milestones to occur on the same day) because this is bad for
our workflow. What is the best way to do this, other than scrolling a Gantt
chart up and down? Is this something that would need to be a VBA macro?
A related problem is that when I do reporting / grouping on our master
schedule, tasks don't make sense out of the context of the project name and
summary task name. Is there any way to do reporting / grouping that
concatenates project name, summary task names, with the job name onto a
single line? I have been playing with the various options without luck.
Thanks for any ideas or starting points.