S
Shafeeq
Hi,
I have some questions ad would appreciate the assistance:
1. Support tasks:
a. How to commit some resources to support (e.g. 40% of their time).
b. how to properly create projects to handle running support tasks, lets
assume a resource is allocated (40% for support).
2. Resources Overallocation:
lets assume a resource is assigned to multiple projects and at the time of
assigning resource to some tasks, we need to identify resource allocation,
a. Does project professional show some sort of status at the time of
allocating the resource to the task or we have to view resource usage sheet
to identify overallocation?
b. The resource allocation sheet shows only resource allocation in the
current project and not in the organization, so does a project manager have
to manually go to pwa and check resource availibility?
3. Task Updates:
at the time a resource submits task update, is there a way to update
percentage complete and number of hours worked at the same time so the system
would adjusted the required working hours on the task?
4. Issues & Risks:
a. is there a way to create simple tabular reports showing list of issues
and risks? or we have to use data analysis views and/or sql reporting
services.
b. For any issue can we have list of actions to be done & history of updates?
5. Timesheets:
a. Whats the use of the "Approval Status" Column in timesheets? it shows
green indicator for administrative lines but nothing appears next to project
tasks evern if the timesheet is approved.
6. Special Roles:
a. we have the concept of sponsors where they are responsible of monitoring
the porject and might need to review and approve some of the document? is
there a way to have the approval process configured without customizations?
b. is there a way to have two project managers on the same project?
7. Migrating Project server 2007:
a. whats the process of migrating PS 2007 from WSS to MOSS 2007? including
movement of databases.
Thanks,
I have some questions ad would appreciate the assistance:
1. Support tasks:
a. How to commit some resources to support (e.g. 40% of their time).
b. how to properly create projects to handle running support tasks, lets
assume a resource is allocated (40% for support).
2. Resources Overallocation:
lets assume a resource is assigned to multiple projects and at the time of
assigning resource to some tasks, we need to identify resource allocation,
a. Does project professional show some sort of status at the time of
allocating the resource to the task or we have to view resource usage sheet
to identify overallocation?
b. The resource allocation sheet shows only resource allocation in the
current project and not in the organization, so does a project manager have
to manually go to pwa and check resource availibility?
3. Task Updates:
at the time a resource submits task update, is there a way to update
percentage complete and number of hours worked at the same time so the system
would adjusted the required working hours on the task?
4. Issues & Risks:
a. is there a way to create simple tabular reports showing list of issues
and risks? or we have to use data analysis views and/or sql reporting
services.
b. For any issue can we have list of actions to be done & history of updates?
5. Timesheets:
a. Whats the use of the "Approval Status" Column in timesheets? it shows
green indicator for administrative lines but nothing appears next to project
tasks evern if the timesheet is approved.
6. Special Roles:
a. we have the concept of sponsors where they are responsible of monitoring
the porject and might need to review and approve some of the document? is
there a way to have the approval process configured without customizations?
b. is there a way to have two project managers on the same project?
7. Migrating Project server 2007:
a. whats the process of migrating PS 2007 from WSS to MOSS 2007? including
movement of databases.
Thanks,