J
JNB
Hi,
How does Project calculate earliest and latest dates (times) for the following
cases ?
Task 1 (predecessor) and Task 2 (successor) linked with Finish-to-Finish or
Start-to-Start dependency with lag or lead time.
I've found a couple of CPM tutorials on the internet but they only contain
examples
of Finish-to-Start dependency. Is there a particular reason for that ?
Thank you in advance for any information.
Best Regards - JNB
How does Project calculate earliest and latest dates (times) for the following
cases ?
Task 1 (predecessor) and Task 2 (successor) linked with Finish-to-Finish or
Start-to-Start dependency with lag or lead time.
I've found a couple of CPM tutorials on the internet but they only contain
examples
of Finish-to-Start dependency. Is there a particular reason for that ?
Thank you in advance for any information.
Best Regards - JNB