Adam

I was wondering if anyone has found a complete field definition list?
I am most interested in finding out what the differences are between "Actual
Work Billable" in the different TimeSheet cubes, as the numbers displayed are
different between the cubes.
 
J

Jack Dahlgren MVP

I do not belive that "Actual Work Billable" is a built-in field, so it may
have been created by whoever configured your installation of Project Server.
If you have administration rights for project server you can log into PWA
and go to Server Settings / Enterprise Custom Field Definition and then look
at how it is defined.

Inserting it into a project file, then right clicking the header and
choosing customize fields will also allow you to look at the field
definition.

If it is not a custom field, then it may be a calculated measure. To see how
it is defined go to Server Settings, Cube configuration then look at the
calculated measure section.

-Jack Dahlgren
 
A

Adam

"Actual Work Billable" must be a built-in field as I configured the system
and I did not create it.
It appears in all of the TimeSheet Cubes. but is only correct in the
"Timesheet" Cube.
I believe that it is a calculated field as it pulls the time from the
various different sections of the timesheets and displays the figures for
each project and administrative time.
Thank you for all of your suggestions I did try them but I cannot display
this field in a project.
 