I want to customize task field Cost1 as Billable Amount
using the formula = (Actual Work * Int. Cost), where Int.
Cost is resource field Cost1. In other words, can you
access resource fields in a customized task field formula?
using the formula = (Actual Work * Int. Cost), where Int.
Cost is resource field Cost1. In other words, can you
access resource fields in a customized task field formula?