Fields in the Group by pick list of Project Center

R

Robert

Hello,

What are the fields listed in the "Group By" pick list in the Project Center
?
I have 2 test servers which display 2 different lists as well for standard
fiels as custom fields.
For ex. one display the Manager, not the other
One displays Checkout and Checked out by, not the other
One display a custom field with a hierarchy, the other has a similar custom
field but doesn't display it.
???
Thanks for any idea
 
D

Dale Howard [MVP]

Robert --

The fields shown on the Group By pick list are the fields contained in the
current View you have applied in the Project Center. If you have the
Summary view applied, for example, you will see the following fields on the
Group By pick list: Project Name, Start, Finish, % Complete, Work,
Duration, and Owner. This is assuming, however, that your Project Server
administrator has not modified the Summary view for the Project Center.
Hope this helps.
 
R

Robert

Dale,

Thanks a lot! I will check that.


Dale Howard said:
Robert --

The fields shown on the Group By pick list are the fields contained in the
current View you have applied in the Project Center. If you have the
Summary view applied, for example, you will see the following fields on
the Group By pick list: Project Name, Start, Finish, % Complete, Work,
Duration, and Owner. This is assuming, however, that your Project Server
administrator has not modified the Summary view for the Project Center.
Hope this helps.
 