Hello everyone,
I have a client that is asking about the fields that can be updated
from PWA. My understanding is that only % Work Complete and Remaining
Hours can be updated (based on Configuration),. Is there ANY way to
allow other fields (Begin Date, end date) to be updated through PWA?
In addition, why do we restrict users to updating % Work Complete and
not % Complete on a task?
Any thoughts are appreciated.