On my system right now, new tasks default task type is Fixed Units and the
"effort driven" box is checked.
When I inserted a new recurring task, each sub-task is Fixed Units and is
NOT effort driven.
When I inserted a new task, that task is Fixed Units and IS effort driven.
I changed it so that the "effort driven" box is UNchecked.
When I inserted a new recurring task, each sub-task is Fixed Units and is
NOT effort driven.
When I inserted a new task, that task is Fixed Units and is NOT effort
driven.
This "sort of" makes sense. The classic example of a recurring task is
the status meeting. No matter how many people you assign to the meeting,
it isn't going to finish sooner. (In fact, meetings might be an Inverse
Effort Driven task: the more people you assign, the longer the meeting
will take!)
JLB, PMP
Hey John, thanks for sticking with me on this.
I have it working as long as I change the effort-driven flag on the
sub-tasks to "Yes".
I'm curious - if you have your options set to New Tasks are Effort
Driven (Tools, Options, Schedule tab), do the sub-tasks under an
inserted recurring task default to effort driven? Mine do not, and I
have to change them manually. Once I do that, the copy/paste (fill
down) command works fine.
Thanks,
Helene
--