K
Kendra
Hi,
I have a resource (Jane) performing Task A (managing sub-contrat) from 10/1
- 10/30 and Task B (another mgmt task, 20% from 10/16 - 11/15). Jane also
has task C, D, each with 40 work hours.
Jane have the remaining 90% availability from 10/1 - 10/15, then 70%
availability from 10/16 - 10/30, then 80% availability from 11/1 - 11/15.
How can I tell MSP to utilize the above available time slots to schedule
task C & some of task D on those free time slot.
Currently, MSP won't schedule task C & D untill 11/16, after task A & B is
completed.
What am I doing wrong?
Thanks,
Candra
I have a resource (Jane) performing Task A (managing sub-contrat) from 10/1
- 10/30 and Task B (another mgmt task, 20% from 10/16 - 11/15). Jane also
has task C, D, each with 40 work hours.
Jane have the remaining 90% availability from 10/1 - 10/15, then 70%
availability from 10/16 - 10/30, then 80% availability from 11/1 - 11/15.
How can I tell MSP to utilize the above available time slots to schedule
task C & some of task D on those free time slot.
Currently, MSP won't schedule task C & D untill 11/16, after task A & B is
completed.
What am I doing wrong?
Thanks,
Candra