V
Verossa
Hi all
I have two almost identical project plans. Many of the tasks / resources are the same - durations / dates differ. I've merged both projects into one plan (insert > project) for cost analysis purposes and created a basic cost filter: Summary equals No AND Baseline Cost is greater than £0.00 (show related summary rows: checked)
The aim of the filter was to develop a graph with two data series for baseline cost i.e. one for each of my projects. This would enable a comparative view of both projects on the same graph. However, the actual output provides one data series with no demarcation by project. Is there a method / technique I can use to develop this
Any advise would be appreciated
TIA - Vers
I have two almost identical project plans. Many of the tasks / resources are the same - durations / dates differ. I've merged both projects into one plan (insert > project) for cost analysis purposes and created a basic cost filter: Summary equals No AND Baseline Cost is greater than £0.00 (show related summary rows: checked)
The aim of the filter was to develop a graph with two data series for baseline cost i.e. one for each of my projects. This would enable a comparative view of both projects on the same graph. However, the actual output provides one data series with no demarcation by project. Is there a method / technique I can use to develop this
Any advise would be appreciated
TIA - Vers