K
Kay
Hi project managers,
one question, because I have never done this,
I have projects planned and resources and tasks setup.
MS P Professional 2003.
Now, we have a budget for deliverables which not necessarily is a one
to one
mapping. Because the projects can be split into several phases.
Example:
Project 1
Deliverable 1
Phase 1
Phase 2
Phase 3
Deliverable 2 Module 1
Phase 1
Phase 2
Phase 3
Project 2
Deliverable 2 Module 2
Phase 1
Phase 2
Phase 3
Now I have to report the resources and the forecasting of their work
based on these budget codes.
So I have to tell controlling, according to my plan, resource x will
spend 50% of her time
on budget code AAAA.
Now, having planned all of this, I thought I enter a custom column
which indicates which budget code is used for each task.
Example:
Project 1
Deliverable 1 Code AAAAA
Phase 1
Phase 2
Phase 3
Deliverable 2 Module 1 Code BBBB
Phase 1
Phase 2
Phase 3
Project 2
Deliverable 2 Module 2 Code BBBB
Phase 1
Phase 2
Phase 3
Support work Code CCCC
Other misc work Code DDDD
Be nice to PM Code CCCC
Then I would run a filter (if this is possible, I don't know), say,
show me all resources for the time period
1.1.2008-31.1.2008
with there person days planned in this time frame or with the % of
their work allocated.
a) is this possible?
b) does my approach make sense?
Kay
one question, because I have never done this,
I have projects planned and resources and tasks setup.
MS P Professional 2003.
Now, we have a budget for deliverables which not necessarily is a one
to one
mapping. Because the projects can be split into several phases.
Example:
Project 1
Deliverable 1
Phase 1
Phase 2
Phase 3
Deliverable 2 Module 1
Phase 1
Phase 2
Phase 3
Project 2
Deliverable 2 Module 2
Phase 1
Phase 2
Phase 3
Now I have to report the resources and the forecasting of their work
based on these budget codes.
So I have to tell controlling, according to my plan, resource x will
spend 50% of her time
on budget code AAAA.
Now, having planned all of this, I thought I enter a custom column
which indicates which budget code is used for each task.
Example:
Project 1
Deliverable 1 Code AAAAA
Phase 1
Phase 2
Phase 3
Deliverable 2 Module 1 Code BBBB
Phase 1
Phase 2
Phase 3
Project 2
Deliverable 2 Module 2 Code BBBB
Phase 1
Phase 2
Phase 3
Support work Code CCCC
Other misc work Code DDDD
Be nice to PM Code CCCC
Then I would run a filter (if this is possible, I don't know), say,
show me all resources for the time period
1.1.2008-31.1.2008
with there person days planned in this time frame or with the % of
their work allocated.
a) is this possible?
b) does my approach make sense?
Kay