Filter comparing project due date & duration

J

Julie

Is there a way to filter tasks for projects where the duration, percent
complete, and due date indicate that they should start today? Ex: if a
project isn't due for 6 weeks but has a 6 week duration & hasn't started yet,
I would want it to show up after the filter in a list of all tasks that are
in danger of getting behind schedule if no progress is made.
 
J

JulieS

Hello Julie,

There are several existing filters that may show you what you need:

Should Start by:
Should Start/Finish By:
Slipped/Late Progress
Slipping Tasks

If you edit the filters, you can view the filter definition and make
modifications as you need.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 