J
Jennifer L
Hello!
I'm trying to create a filter or field (whatever does the trick) to do the
following:
I have a schedule that runs from June 2008 to June 2010. I need to capture
Work for (our) fiscal year 2009 - so the date range would be 12/1/08 -
11/30/09. My problem is when I filter for that Date Range I still get all of
the work assigned to those tasks. I would like for Project to ignore the work
done outside of the FY2009 dates, eg: if a task runs from 10/1/08 - 3/31/09,
I want to see Work hours assigned on this task only from 12/1/08 - 3/31/09
and ignore the work done from 10/1/08 - 11/30/08.
Can I build a filter or formula to do this? Or is a macro needed?
Please help.
Thank you!
Jennifer
I'm trying to create a filter or field (whatever does the trick) to do the
following:
I have a schedule that runs from June 2008 to June 2010. I need to capture
Work for (our) fiscal year 2009 - so the date range would be 12/1/08 -
11/30/09. My problem is when I filter for that Date Range I still get all of
the work assigned to those tasks. I would like for Project to ignore the work
done outside of the FY2009 dates, eg: if a task runs from 10/1/08 - 3/31/09,
I want to see Work hours assigned on this task only from 12/1/08 - 3/31/09
and ignore the work done from 10/1/08 - 11/30/08.
Can I build a filter or formula to do this? Or is a macro needed?
Please help.
Thank you!
Jennifer