M
Mike H Le
I have tried playing around with this code, but cannot get
it to work.
1. Filter out those future tasks (task will start
next month), and code "4" in the number2 field.
2. Filter out next week tasks (tasks start or finish
next week), and code "3" in the number2 field.
3. Filter out in-progress tasks (between 1% to 99%),
and code "2" in the number2 field.
4. Filter out this week tasks (tasks start or finish
this week), and code "1" in the number2 field
5. Group number2 field.
If you have some similar code, Please help. Thanks
Mike H Le
it to work.
1. Filter out those future tasks (task will start
next month), and code "4" in the number2 field.
2. Filter out next week tasks (tasks start or finish
next week), and code "3" in the number2 field.
3. Filter out in-progress tasks (between 1% to 99%),
and code "2" in the number2 field.
4. Filter out this week tasks (tasks start or finish
this week), and code "1" in the number2 field
5. Group number2 field.
If you have some similar code, Please help. Thanks
Mike H Le