Has anyone developed a filter (MSP 2007) to show all the tasks linked to a
given task? I have done this by inserting a deadline that turns all the
predecessor linked tasks critical, however a custom filter would be much
better. Project has this calculation built in to identify the circular link
error, but does not provide access to it as a filter. This would be very
useful for analysis.