Filtered Hours Worked Report

  • Thread starter Andy Rutherford
  • Start date
A

Andy Rutherford

Project Gurus,

I am working on a large project which has ~1,000 consultants using Project
Server of which ~50 work for me. The client's PMO is administering Project
Server so I don't have direct access. My company uses its own time tracking
system and since this is a T&M project, we have a single code we use in our
internal time tracking system to log time whereas time entered into Project
Server is done so against work plans and tasks.

Before I can invoice the client, I need to reconcile the two. To do that, I
need a monthly report from Project Server which will show only our
consultants (prefereably read from a text file/database table since we aren't
flagged as any different in PS and our consulting workforce is somewhat
dynamic).

The report should prompt for the Month/Year in question and include a column
for each day in that month, rows for resource name and a summary of hours
worked on that day across all work plans as the cell data.

My assumption is that this would require custom development and I'm willing
to pay for the service to build it. I am in Melbourne Australia and would
prefer to have someone here but we could potentially get remote access. If
anyone has any suggestoins, please let me know by emailing to
(e-mail address removed).

Thanks in advance,
Andy
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top