M
Misha
Hello,
I have a task A and task B.
Task A has subtasks A1 and A2. A2 in turn has substasks A21 and A22.
Task B has subtask B1. A22 starts when B1 completes.
How do I define filtering criteria to show all subtasks of A plus all tasks
which are not subtasks of A but on which any of A's subtasks depend (B1)?
Basically I have 2 projects A and B and the order of subtasks is mixed
between the 2 projects. Sometimes I need to report only on taks A and that
set should also contain all tasks on which any of A's subtask depend.
However I do not need to show more than 1 task going back in the time line.
So for example if B1 depened on B0, I want to see B1 but not B0 when I
report on A.
Thanks,
Misha
I have a task A and task B.
Task A has subtasks A1 and A2. A2 in turn has substasks A21 and A22.
Task B has subtask B1. A22 starts when B1 completes.
How do I define filtering criteria to show all subtasks of A plus all tasks
which are not subtasks of A but on which any of A's subtasks depend (B1)?
Basically I have 2 projects A and B and the order of subtasks is mixed
between the 2 projects. Sometimes I need to report only on taks A and that
set should also contain all tasks on which any of A's subtask depend.
However I do not need to show more than 1 task going back in the time line.
So for example if B1 depened on B0, I want to see B1 but not B0 when I
report on A.
Thanks,
Misha