filtering in pwa

M

moe

I have a user who is seeing a nested level of dates that noone else is seeing
in the group - can someone please help me understand what setting she must
have accidentally toggled?

Thanks
 
D

Dale Howard [MVP]

moe --

You might want to tell us what version of Project Server you are using
(2002, 2003, or 2007) and WHERE the user sees the nested levels of dates in
PWA (My Tasks page, Project Center page, etc.). For the moment, I will
assume you are using Project Server 2007 and the user sees the nested dates
on the My Tasks page in PWA. Assuming this is the case, ask the user to do
the following:

1. Log into PWA and navigate to the My Tasks page.
2. Click the Settings menu and select the Group iten on the menu.

My guess is that the user has the Group By and/or Then By values set to
either the Start or Finish fields.

3. Set the Group By and the Then By pick list values to the blank item (top
of the list) and then click the Apply button.

Let us know if this resolves the user's problem, or if my assumptions are
incorrect.
 
B

Ben Howard

Hi Moe,

The Group By field is the one that provides the nested view. Therefore your
user is probably grouping by Start Date or Finish Date.
 
M

moe

Hi Dale,

This worked like a charm (although the user says she never changed this
filter in the first place).

Thanks Moe
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top