J
jlbreyer
Each functional manager (electrical, mechanical, software, etc.) wants to
review the work hours planned for each phase of the project, with summary
rollup for just the group of interest. I can view Task Usage and filter for
one resource group, but the rollups show hours for all reesources. Is there
a way to show task usage with work for just one category shown, with rollups
for just that category?
I am using Project Pro 2003 with Project Server 2003 and PWA.
Is there an alternative way to show subset resource hours within the WBS?
review the work hours planned for each phase of the project, with summary
rollup for just the group of interest. I can view Task Usage and filter for
one resource group, but the rollups show hours for all reesources. Is there
a way to show task usage with work for just one category shown, with rollups
for just that category?
I am using Project Pro 2003 with Project Server 2003 and PWA.
Is there an alternative way to show subset resource hours within the WBS?