Filtering Tasks by Date

S

SloopJohnB

Can I filter the tasks that are active in a time period say 1200 hrs 13
Sept to 1200 hrs 14 Sept?

I would like to see the tasks that have started before and during that
period, finish during that period and run though that period.

Thanks for your assistance.
 
M

Mike Glen

Hi SloopJohnB,

Welcome to this Microsoft Project newsgroup :)

Use the Date Range... filter. Having selected the date, type in 12:00 after
the date to include the time.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 