D
Dann
I am attempting to create a custom view based on the "Resource Usage" view.
(Ultimately, it will printed as a report.) The basic view shows each resource
and the tasks assigned to that resource. I can include any number of task
fields such as baseline start, start, actual start, etc. What I can't do is
filter the tasks to show just a sub-set.
If I am working in a task view I have custom field that uses a formula to
determine which tasks are either current or scheduled to begin within the
next two weeks. (Thanks to zo-d.com/blog/archives/ms-project-tips.html)
However, when I attempt to apply this filter to the resource view nothing
happens.
I then tried to create the same formula in a resource filter, but that
didn't work either as it is looking at the % work complete for the resource
and not the individual tasks. Is there anyway to filter the tasks that show
in this view?
(Ultimately, it will printed as a report.) The basic view shows each resource
and the tasks assigned to that resource. I can include any number of task
fields such as baseline start, start, actual start, etc. What I can't do is
filter the tasks to show just a sub-set.
If I am working in a task view I have custom field that uses a formula to
determine which tasks are either current or scheduled to begin within the
next two weeks. (Thanks to zo-d.com/blog/archives/ms-project-tips.html)
However, when I attempt to apply this filter to the resource view nothing
happens.
I then tried to create the same formula in a resource filter, but that
didn't work either as it is looking at the % work complete for the resource
and not the individual tasks. Is there anyway to filter the tasks that show
in this view?