T
Tris
Is it possible to change the start the date the week number starts from as my
companies start date is differnet to MS Project?
For example MS Project says that 3rd Jan 2006 is in Week 14 while my company
Financial Calendar says it's in Week 15!
I've set the machine to have the financial year starting in October and all
our production weeks start with week one being 29th September 2005
Cheers
companies start date is differnet to MS Project?
For example MS Project says that 3rd Jan 2006 is in Week 14 while my company
Financial Calendar says it's in Week 15!
I've set the machine to have the financial year starting in October and all
our production weeks start with week one being 29th September 2005
Cheers