C
Clive
Hi,
Running MS-Project 2000.
For individual tasks, as far as keeping on schedule is concerned,
the PM is less interested in the work done, it is the estimated
effort/time required to finish the task that is important.
Example.
We estimated a 5 day task. 3 days work has been done - that's fine
for billing the work down. However, I really want the actuals to also
tell me that the resource feels that 3 MORE days are needed to complete
the task.
In which field can I enter this "Days to Complete" estimate for a
task - and how can I display it so that it becomes visible that the
completion date will be overrun for that task?
Thanks
Clive
Running MS-Project 2000.
For individual tasks, as far as keeping on schedule is concerned,
the PM is less interested in the work done, it is the estimated
effort/time required to finish the task that is important.
Example.
We estimated a 5 day task. 3 days work has been done - that's fine
for billing the work down. However, I really want the actuals to also
tell me that the resource feels that 3 MORE days are needed to complete
the task.
In which field can I enter this "Days to Complete" estimate for a
task - and how can I display it so that it becomes visible that the
completion date will be overrun for that task?
Thanks
Clive