Finding out tasks to be complete in a particular period

  • Thread starter prashanth.sharangapani
  • Start date
P

prashanth.sharangapani

Dear Friends,

How do I find out what tasks should be complete next week?

Thanks,
Prashanth
 
J

Jan De Messemaeker

Hi,

Activate the auto filter
On the finish field use Custom..
Use "Is greater than or equal to" ... (next monday)
AND
"Is less that or equal to" ... (friday next week)

instead of (monday next week) and (friday next week) use the dates.

HTH

--
Jan De Messemaeker