P
Pierre
I have assigned two resources on a task. Resource A works 50% (mornings) and
resource B 80% (not on Fridays).
The task I have assigned to them starts on 3 September, according to my
plan. The overall effort is one day, which leads to .92 days, based on A & B'
schedules.
B is on holiday from 4 September and back in the office on 14 September.
During that time, A is working normally, according to her schedule.
I cannot explain why MS Projects calculates the end of the task on 14
September, as A is free to work at her pace whilst B is on holiday. It should
be finished by September 4. It is as if A cannot work if B is on holiday.
I am obviously doing something wrong. But what???
resource B 80% (not on Fridays).
The task I have assigned to them starts on 3 September, according to my
plan. The overall effort is one day, which leads to .92 days, based on A & B'
schedules.
B is on holiday from 4 September and back in the office on 14 September.
During that time, A is working normally, according to her schedule.
I cannot explain why MS Projects calculates the end of the task on 14
September, as A is free to work at her pace whilst B is on holiday. It should
be finished by September 4. It is as if A cannot work if B is on holiday.
I am obviously doing something wrong. But what???