G
Garon
We have set [Tools | Options | Calculation Tab ]
"Move end of completed parts after status back to status date" flag to
checked
However when we update a task to 100% complete with a Finish Date planned to
a date in the future, then approve the Status Update the Finish Date is being
set to a date one day prior to the status date.
The [Project | Project Information | Current Date] = "Fri 5/08/05" (Today's
Date)
The [Project | Project Information | Status Date] = "NA" (ie blank)
The [Task Information | Start] = "Fri 5/08/05"
The [Task Information | Duration] = "7 Days"
On "Fri 5/08/05" we set the Task Status to 100% complete in PWA. The
Manager then approves the Status Update on "Fri 5/08/05".
This should set the Finish Date to "Fri 5/08/05", but it is setting it to
"Thu 4/08/05".
If we set [Project | Project Information | Status Date] = "Fri 5/08/05"
and redo the test we are presented with a pompt advising the Status Date is
nt equal to the Current Date and asking which date do we want to use. The
Current Date in Project Information is definitely set to "Fri 5/08/05". The
dates shown in PWA for the Date the Status Update was sent for approval is
showing "Fri 5/08/05".
The Project Professional client workstation has a system date of "Fri
5/08/05".
The Project Server & SQL Server (SBS) has a system date of "Fri 5/08/05"
The [Task Information | Advanced Tab | Constraint Type] = "As Soon as
Possible"
The [Task Information | Advanced Tab | Task Type] = "Fixed Units"
The [Task Information | Advanced Tab | Effort Driven] = "Checked"
The [Task Information | Advanced Tab | Calendar] = "Standard"(Inchanged)
The Resource Calendar is also set to Standard
Has anyone had a similar experience. It is critical to our operations that
the "Finish Date" is set accurately to the Current Date.
"Move end of completed parts after status back to status date" flag to
checked
However when we update a task to 100% complete with a Finish Date planned to
a date in the future, then approve the Status Update the Finish Date is being
set to a date one day prior to the status date.
The [Project | Project Information | Current Date] = "Fri 5/08/05" (Today's
Date)
The [Project | Project Information | Status Date] = "NA" (ie blank)
The [Task Information | Start] = "Fri 5/08/05"
The [Task Information | Duration] = "7 Days"
On "Fri 5/08/05" we set the Task Status to 100% complete in PWA. The
Manager then approves the Status Update on "Fri 5/08/05".
This should set the Finish Date to "Fri 5/08/05", but it is setting it to
"Thu 4/08/05".
If we set [Project | Project Information | Status Date] = "Fri 5/08/05"
and redo the test we are presented with a pompt advising the Status Date is
nt equal to the Current Date and asking which date do we want to use. The
Current Date in Project Information is definitely set to "Fri 5/08/05". The
dates shown in PWA for the Date the Status Update was sent for approval is
showing "Fri 5/08/05".
The Project Professional client workstation has a system date of "Fri
5/08/05".
The Project Server & SQL Server (SBS) has a system date of "Fri 5/08/05"
The [Task Information | Advanced Tab | Constraint Type] = "As Soon as
Possible"
The [Task Information | Advanced Tab | Task Type] = "Fixed Units"
The [Task Information | Advanced Tab | Effort Driven] = "Checked"
The [Task Information | Advanced Tab | Calendar] = "Standard"(Inchanged)
The Resource Calendar is also set to Standard
Has anyone had a similar experience. It is critical to our operations that
the "Finish Date" is set accurately to the Current Date.