T
tw_webex
I want to set a "flexible" Finish Date that is updated automatically if I
update a milestone/end date for a linked task.
E.g. I have set the normal Start and Finish Dates for a project. I have
also set milestones/end dates for several Tasks. One of those Tasks,
however, will determine the acutal Finish Date of the entire project. So, if
I change the milestone/end date of the determinant Task, I would like the
Finish Date to update automatically by adding 60 days to the new
milestone/end date of the determinant Task and set the new Finish Date.
Is this possible/
Thx!
update a milestone/end date for a linked task.
E.g. I have set the normal Start and Finish Dates for a project. I have
also set milestones/end dates for several Tasks. One of those Tasks,
however, will determine the acutal Finish Date of the entire project. So, if
I change the milestone/end date of the determinant Task, I would like the
Finish Date to update automatically by adding 60 days to the new
milestone/end date of the determinant Task and set the new Finish Date.
Is this possible/
Thx!