I used VBA to import the following fields from my contractor
schedule into my published Project Server schedule:
Duration
Start
Finish
Predecessors
Successors
Calendar
% Complete
Actual Start
Actual Finish
Actual Duration
Remaining Duration
Constraints
Once imported, I noticed that the duration of each in progress task in the
project server schedule is always slightly off (usually less than 1.5 days)
from the contractor schedule. The contractor did resource loaded the
schedule. The assignment unit seems to be the same. Any recommendation is
appreciated.
Thank you in advance.
schedule into my published Project Server schedule:
Duration
Start
Finish
Predecessors
Successors
Calendar
% Complete
Actual Start
Actual Finish
Actual Duration
Remaining Duration
Constraints
Once imported, I noticed that the duration of each in progress task in the
project server schedule is always slightly off (usually less than 1.5 days)
from the contractor schedule. The contractor did resource loaded the
schedule. The assignment unit seems to be the same. Any recommendation is
appreciated.