finish dates have a mind of their own!!

C

chu

hello all,

the task dates in our group project are always changing. it's mostly the
finish date that gets changed and it's a wacky date like 2048 or something.

also can some one verify a suspicion of mine?

a project view (say gantt) is closed/saved with sort/filter options applied
that were'nt in place when opened, this can throw people off the next time
they open the file? plz explain.
 
J

JulieS

Hi chu,

A couple of guesses/questions:

Do you have resources assigned to summary tasks?
Do you have you Resource Leveling set to automatic?

Julie
 
C

chu

thanks for getting back to me julie, the answer to
your questions are no.
have to go, maybe we can pick up mon morning?
chu
 
J

JulieS

Hi chu,

Sorry, I'm off line on Monday and Tuesday. Post some more information
on Monday morning and perhaps someone else will jump in.

Julie
 
S

Steve House [Project MVP]

Sounds like you have an endless loop somewhere, perhaps a SF link, an ALAP
constraint, or a link to a hammock task that sends the date out until it
overflows at the last possible date in Project, 12/31/2049.
 
C

chu

steve - thanks for the reply, but could you explain in layman terms?
i'm new at this. thanks again.

chu

Steve House said:
Sounds like you have an endless loop somewhere, perhaps a SF link, an ALAP
constraint, or a link to a hammock task that sends the date out until it
overflows at the last possible date in Project, 12/31/2049.

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs

chu said:
thanks for getting back to me julie, the answer to
your questions are no.
have to go, maybe we can pick up mon morning?
chu
 
J

Jan De Messemaeker

Hi,

Sure, very very sure you didn't do leveling (automatic or manual)
There are instances when leveling does that.
Look for the availability of the resources as shown under Resource
Information.
When there's a resource whose availability stops and leveling pushes a task
into the timespan after its availability the end date ends up to be Dec 31,
2049.

HTH
--
Jan De Messemaeker, Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
For FAQs: http://www.mvps.org/project/faqs.htm
chu said:
steve - thanks for the reply, but could you explain in layman terms?
i'm new at this. thanks again.

chu

Steve House said:
Sounds like you have an endless loop somewhere, perhaps a SF link, an ALAP
constraint, or a link to a hammock task that sends the date out until it
overflows at the last possible date in Project, 12/31/2049.

--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs

chu said:
thanks for getting back to me julie, the answer to
your questions are no.
have to go, maybe we can pick up mon morning?
chu

:

Hi chu,

A couple of guesses/questions:

Do you have resources assigned to summary tasks?
Do you have you Resource Leveling set to automatic?

Julie
hello all,

the task dates in our group project are always changing. it's mostly
the
finish date that gets changed and it's a wacky date like 2048 or
something.

also can some one verify a suspicion of mine?

a project view (say gantt) is closed/saved with sort/filter options
applied
that were'nt in place when opened, this can throw people off the next
time
they open the file? plz explain.
 