C
chicory
Hi,
I'm new to Microsoft Project and have been working my way through all the
tutorials but haven't come across an answer to this yet.
I entered tasks, durations, resources, and then linked tasks and set
dependencies. Then, I realized it was difficult to discuss the schedule with
others (with 40 tasks), so I started grouping tasks into phases with summary
task names.
Now, what I'd like is for Project to re-order the work so that tasks in a
phase finish in order, making the duration of each phase as short as
possible. If there's a good reason for doing something from Phase 2 right
away, that's fine, but if there's no reason to do a task from Phase 2, I'd
like to work my way through all the tasks in Phase 1 before moving on.
How would you deal with this? Set priorities? Create some (not really
accurate) dependency? Or something else?
Thanks for any advice you can offer!
I'm new to Microsoft Project and have been working my way through all the
tutorials but haven't come across an answer to this yet.
I entered tasks, durations, resources, and then linked tasks and set
dependencies. Then, I realized it was difficult to discuss the schedule with
others (with 40 tasks), so I started grouping tasks into phases with summary
task names.
Now, what I'd like is for Project to re-order the work so that tasks in a
phase finish in order, making the duration of each phase as short as
possible. If there's a good reason for doing something from Phase 2 right
away, that's fine, but if there's no reason to do a task from Phase 2, I'd
like to work my way through all the tasks in Phase 1 before moving on.
How would you deal with this? Set priorities? Create some (not really
accurate) dependency? Or something else?
Thanks for any advice you can offer!