Finish in PWA View a Project not including holidays

D

Doc

I have discovered that the Finish date in the PWA Project Center, when
viewing a specific project to be different that the Finish date in the
Project Professional 2003 tool (i.e. the task is completed one day
earlier than it should). I am setting holidays in the Enterprise global
and forcing the project plan to use that calendar.

When I publish the task, the Finish date is correct in the My Tasks
view for the recepient of the assignment.

Has anyone else seen this?

I am at SP1 maintenance on both Project Server and Project Professional
2003.

Regards
Doc

Mark Dochtermann
Senior Instructor
www.iil.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top