I have discovered that the Finish date in the PWA Project Center, when
viewing a specific project to be different that the Finish date in the
Project Professional 2003 tool (i.e. the task is completed one day
earlier than it should). I am setting holidays in the Enterprise global
and forcing the project plan to use that calendar.
When I publish the task, the Finish date is correct in the My Tasks
view for the recepient of the assignment.
Has anyone else seen this?
I am at SP1 maintenance on both Project Server and Project Professional
2003.
Regards
Doc
Mark Dochtermann
Senior Instructor
www.iil.com
viewing a specific project to be different that the Finish date in the
Project Professional 2003 tool (i.e. the task is completed one day
earlier than it should). I am setting holidays in the Enterprise global
and forcing the project plan to use that calendar.
When I publish the task, the Finish date is correct in the My Tasks
view for the recepient of the assignment.
Has anyone else seen this?
I am at SP1 maintenance on both Project Server and Project Professional
2003.
Regards
Doc
Mark Dochtermann
Senior Instructor
www.iil.com