C
Chris
Dear All,
Any guidance would be welcomed concerning constraints for this particular
scenario.
I have 10 tasks, A-J.
Tasks A-E are linked by 'finish-start' dependencies and are also 'as late as
possible' constrained.
Task F must finish no later than 31st Mar 2015. It is linked by a
'finish-start' dependency to previous Task E and also a 'finish-start'
dependency to subsequent Task G
Tasks G-J are linked by 'finish-start' dependencies and are also 'as soon as
possible' constrained.
I am unable to make Task F take up the finish date of 31st Mar 2015. It is
earlier - which I assume is correct as it must occur before that date.
However, I would have assumed that it would have been pushed back to that
date by the previous 'as late as possible constraints for Tasks A-E.
I converted Task F to a 'must finish on' constraint to see if this forces
the date to be 31st Mar 2015 but that doesn't seem to have the desired effect.
I also looked at the deadline function but am aware that this is more
advisory than constraining.
The confusing thing is that I have other projects that seem to take up this
constraint fine. I've checked to see if I have inadvertantly got links in
place which are causing the shift but cannot see anything untoward.
There is a !note in the information column which says "This task finishes on
30/01/12 which is different than its 'Must Finish On' constraint of 31/03/15".
I do need this task to finish on that specific date (perishable goods
leaving warehouse) - any guidance would be welcomed.
Regards
Chris
Any guidance would be welcomed concerning constraints for this particular
scenario.
I have 10 tasks, A-J.
Tasks A-E are linked by 'finish-start' dependencies and are also 'as late as
possible' constrained.
Task F must finish no later than 31st Mar 2015. It is linked by a
'finish-start' dependency to previous Task E and also a 'finish-start'
dependency to subsequent Task G
Tasks G-J are linked by 'finish-start' dependencies and are also 'as soon as
possible' constrained.
I am unable to make Task F take up the finish date of 31st Mar 2015. It is
earlier - which I assume is correct as it must occur before that date.
However, I would have assumed that it would have been pushed back to that
date by the previous 'as late as possible constraints for Tasks A-E.
I converted Task F to a 'must finish on' constraint to see if this forces
the date to be 31st Mar 2015 but that doesn't seem to have the desired effect.
I also looked at the deadline function but am aware that this is more
advisory than constraining.
The confusing thing is that I have other projects that seem to take up this
constraint fine. I've checked to see if I have inadvertantly got links in
place which are causing the shift but cannot see anything untoward.
There is a !note in the information column which says "This task finishes on
30/01/12 which is different than its 'Must Finish On' constraint of 31/03/15".
I do need this task to finish on that specific date (perishable goods
leaving warehouse) - any guidance would be welcomed.
Regards
Chris