Help. I have a project were a task is set finish to start. Its predecessor
finishes at 22/01/08 13:00. The task is set for 12 hours and rightly sets
the start time as 22/01/08 13:00. The finish time then changes to 23/01/08
13:00. I want this to be 23/01/08 01:00. I have tried changing the Task
Information > Advanced and calendar to 24hrs but it will not allow me to put
01:00. I have tried each calendar option, I have set the working day to
12hrs for a 07:00 to 19:00 finish. I have removed the link but still it does
not work. Does anyone have an idea or someone I could email it to try?
Thanks
finishes at 22/01/08 13:00. The task is set for 12 hours and rightly sets
the start time as 22/01/08 13:00. The finish time then changes to 23/01/08
13:00. I want this to be 23/01/08 01:00. I have tried changing the Task
Information > Advanced and calendar to 24hrs but it will not allow me to put
01:00. I have tried each calendar option, I have set the working day to
12hrs for a 07:00 to 19:00 finish. I have removed the link but still it does
not work. Does anyone have an idea or someone I could email it to try?