M
Mikkel
Hi,
I'm working on a project where I have several tasks where the successor (B)
can't finish until the predecessor (A) finishes. That I thought was a
finish-to-finish dependency. But Project (2007) now forces the B to finish
the same time as the A! I only need A to be finished BEFORE B finishes, not
necessarily the same time.
How do I do this?
Thanks,
Mikkel
I'm working on a project where I have several tasks where the successor (B)
can't finish until the predecessor (A) finishes. That I thought was a
finish-to-finish dependency. But Project (2007) now forces the B to finish
the same time as the A! I only need A to be finished BEFORE B finishes, not
necessarily the same time.
How do I do this?
Thanks,
Mikkel