C
Chris
Dear All,
I'd welcome some help please.Would
I have 2 projects A, B, each with 5 tasks 1,2,3,4,5 each with different
durations for projects A and B. Each task within the project has a Finish to
Start link. Each task should start straight after its predecessor (i.e.
within 24 hours).
Tasks A3 and B4 must finish at the same time, so I have assumed that they
would use a Finish to Finish link. However, although this seems to work it
stops the neat stacking of tasks B1,B2,B3 and B4, they become disjointed with
large gaps between some of their ends and the start of the next task.
Tasks B1, B2, B3 have no date constraints on them so I'm wondering how I can
get this smooth move between those tasks whilst retaining the Finish to
Finish constraint (which also does not have a date constraint).
Many thanks for help / views in advance.
Chris
I'd welcome some help please.Would
I have 2 projects A, B, each with 5 tasks 1,2,3,4,5 each with different
durations for projects A and B. Each task within the project has a Finish to
Start link. Each task should start straight after its predecessor (i.e.
within 24 hours).
Tasks A3 and B4 must finish at the same time, so I have assumed that they
would use a Finish to Finish link. However, although this seems to work it
stops the neat stacking of tasks B1,B2,B3 and B4, they become disjointed with
large gaps between some of their ends and the start of the next task.
Tasks B1, B2, B3 have no date constraints on them so I'm wondering how I can
get this smooth move between those tasks whilst retaining the Finish to
Finish constraint (which also does not have a date constraint).
Many thanks for help / views in advance.
Chris