Finish Variance field

R

Robert

Does the Finish Variance field automatically compensate for multiple
baselines? If not, how does that impact graphic indicators on projects where
a 2nd baseline is saved?
 
D

Dale Howard [MVP]

Robert --

The Finish Variance field displays finish variance using the following
formula:

Finish Variance = Finish - Baseline Finish

Even if you save baselines in any of the Baseline1-10 fields, the Finish
Variance formula will still calculate finish variance using the Baseline
Finish field. If you need to calculate finish variance using any of the
Baseline1-10 fields, you must do so by using a formula in a custom Duration
field. Hope this helps.
 